TABLE
2
GOALS ACHIEVEMENT MATRIX DEVELOPMENT OF UNDERUTILIZED LAND |
|||||||||||
ACTIVITY |
IN PROGRESS |
ESTIMATED TIMING |
IN PREVIOUS IMPLEMENTATION PLAN? |
ESTIMATED COST ($) |
NET TAX INCREMENT POTENTIAL |
PROJECT AREA NO. 1 |
MERGED & AMENDED PROJECT |
CONDITIONS OF BLIGHT ADDRESSED (See Section 2.1.2) |
GOALS & OBJECTIVES ADDRESSED (See Section 3.1) |
||
|
|||||||||||
1. |
Continue negotiations for Cal Compact site (Carson Outlet Mall) |
Y |
2000 |
Y |
18,000,000 (Loan) |
Moderate |
Y |
N |
A, K, L, N, O |
1, 2, 3, 4, 8, 9, 13, 15, 16, 17, 18, 20 |
|
2. |
Implementation of DDA for Home Depot Center |
Y |
2000 |
N |
2,400,000 |
Moderate |
N |
Y |
E, K, L, O |
1, 2, 3, 4, 8, 9, 13, 16, 17, 18, 20 |
|
3. |
Identify use and commence DDA/OPA for Albertoni Hotel property |
N |
2000-2001 |
Y |
3,000,000 |
High |
Y |
N |
A, B, C, K, L, M, O |
1, 2, 3, 4, 5, 6, 8, 9, 11, 13, 14, 15, 16, 17, 18, 20 |
|
4. |
Identify use and commence DDA/OPA for Try-It Discount Mall and adjacent vacant property on Avalon Boulevard at 228th Street |
N |
2000-2001 |
N |
n/a |
High |
N |
Y |
A, B, C, K, L, M, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 17, 18, 20 |
|
5. |
Identify use and commence DDA/OPA for commercial property on Main Street at 220th Street |
N |
2000-2001 |
N |
n/a |
Moderate |
Y |
N |
A, B, C, K, L, M, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 17, 18, 20 |
|
6. |
Auto-row development on 223rd Street (Wilmington Avenue to Alameda Street) |
N |
2000-2001 |
N |
1,000,000 |
High |
N |
Y |
A, B, C, F, K, L, M, N, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 18, 20 |
|
7. |
Surface-street traffic study: 223rd/Wilmington area |
N |
2000-2001 |
N |
500,000 |
High |
N |
Y |
A, B, C, F, K, L, M, N, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 18, 20 |
|
8. |
Identify use and commence DDA/OPA for Alpert & Alpert/Clean Steel site |
N |
2000-2003 |
N |
2,000,000 |
High |
N |
Y |
A, B, F, H, K, L, M, N, O, P |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 18, 20 |
|
9. |
Identify use and commence DDA/OPA for South Bay Six Drive-In and adjacent 5-acre site |
N |
2000-2003 |
N |
2,000,000 |
High |
Y |
N |
A, B, C, J, K, L, M, N, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 6, 18, 20 |
|
10. |
Identify use and commence DDA/OPA for site on Figueroa at Albertoni Street |
N |
2000-2002 |
N |
1,000,000 |
Moderate |
Y |
N |
A, B, C, K, L, M, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 17, 18, 20 |
|
11. |
Continue implementation of ARCO OPA |
Y |
2000-2004 |
N |
4,000,000 |
High |
Y |
N |
A, B, C, D, E, G, I, J, K, L, N, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 17, 18, 20 |
|
|
|||||||||||
12. |
Proposed development on Figueroa at 91 Freeway |
N |
2001-2002 |
N |
n/a |
High |
Y |
N |
A, B, C, F, K, L, M, N, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 18, 20 |
|
13. |
Identify use and commence DDA/OPA for Carson Town Center |
N |
2001-2002 |
N |
2,000,000 |
High |
Y |
N |
E, K, L, O |
1, 2, 3, 4, 8, 9, 13, 14, 16, 18, 20 |
|
14. |
Identify use and commence DDA/OPA for El Camino Business Park, adjacent 14-acre site and others |
N |
2002-2003 |
N |
2,000,000 |
Moderate |
Y |
N |
A, B, C, D, E, G, I, J, K, L, N, O |
1, 2, 3, 4, 8, 9, 10, 13, 14, 15, 16, 18, 20 |
|
15. |
Identify use and commence DDA/OPA for Shell Oil site |
N |
2001-2004 |
N |
n/a |
High |
Y |
N |
A, B, C, K, L, M, N, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 18, 19, 20 |
|
16. |
Identify use and commence DDA/OPA for Fletcher Oil site |
N |
2002-2004 |
N |
n/a |
High |
N |
Y |
A, B, C, F, K, L, M, N, O |
1, 2, 3, 4, 8, 9, 13, 14, 15, 16, 18, 20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
LEVEL THREE ACTIVITIES (Projects commencing 2003
or 2004) - NONE
|