LEVEL ONE ACTIVITIES (Continuing projects or projects commencing in 2000)

17.

Initiate construction of Magic Johnson Theaters (Carson Mall Partners OPA)

N

2000-2001

N

5,000,000

High

Y

N

K, L, O

1, 2, 3, 4, 8, 13, 16, 17, 18, 20

18.

Conduct traffic/land uses studies at I-405/Wilmington interchange

N

2000

N

100,000-200,000

Low

N

Y

J, P

1, 2, 10, 19

19.

Attract quality restaurants

N

2000-2001

N

2,000,000

Moderate

Y

Y

K

2, 3, 4, 8, 13, 14, 16, 18, 20

20.

Conduct study to address barriers to surface-street circulation, i.e., freeways, railroads, and Dominguez Channel

This activity was identified by the Carson Economic Development Committee as a potential Redevelopment Agency project.  Agency staff, however, considers this to be an issue best addressed by the Traffic and Circulation Element of the Carson General Plan, or in conjunction with other traffic/land use studies identified this Implementation Plan. 

21.

Friendship Children’s Center

N

2000-2001

N

1,000,000

Moderate

N

Y

K, L, O

1, 2, 3, 8, 10, 18, 20

22.

Lucas Brothers Development

N

2000-2001

N

50,000

Moderate

N

Y

K, L, O

1, 2, 3, 8, 10, 18, 20

23.

Teen Center Partnership Program

N

2000-2002

N

3,000,000

Moderate

N

Y

K, L, O

1, 2, 3, 8, 10, 18, 20

24.

Alameda Street/Alameda corridor rehabiilitation and development between Carson and Dominguez Streets.  Includes conduct/expand studies: 

·    Land use

·    Noise

·    Engineering

·    Traffic and circulation

N

2000-2004

N

n/a

High

N

Y

All

1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20

25.

Alameda corridor soundwall

·    Feasibility Study

·    Soundwall construction

N

2000-2001

N

50,000

Low

N

Y

All

1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20

26.

Carson Street rehabilitation and development between I-110 and I-405:

·    Land assembly

·    Public improvements

·    Specific Plan for public and private development

·    Possible expansion of redevelopment project area

N

2000-2004

N

9,000,000

High

Y

N

All

1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20

27.

Conduct study of ‘e-commerce’ and its potential application in Carson

N

2000-2002

N

60,000

Low

Y

Y

n/a

4, 8, 10, 12, 13, 16, 18, 20

28.

Consolidate sub-standard or irregular parcels for modern development

N

2000-2004

Y

n/a

High

Y

Y

D, E, G, H, I, K, L, O, P

1, 2, 3, 4, 8, 13, 14, 20

29.

Develop comprehensive housing strategy

Y

2000-2001

N

50,000-100,000

Low

Y

Y

J, K

1, 2, 3, 4, 5, 6, 8, 10, 11, 18, 20

30.

Dominguez Channel Multi-Use Enhancement Study

N

2000-2002

N

50,000

Low

Y

Y

2, 20

 

 

 

 

 

 

 

 

 

 

 

 

LEVEL TWO ACTIVITIES (Projects commencing 2001 or 2002)

31.

Abatement of inappropriate uses north of 91 Freeway

N

2002-2004

N

n/a

High

Y

N

All

1, 2, 3, 4, 8, 9, 10, 12, 13, 14, 15, 16, 18, 19, 20

32.

Develop neighborhood-oriented commercial services along Main Street and Broadway between I-405 and Alondra Boulevard

N

2002-2004

N

n/a

Moderate

Y

N

K

2, 3, 4, 8, 13, 14, 16, 18, 20

33.

Develop a rehabilitation and improvement study for Sepulveda Boulevard between Main Street and Avalon Boulevard

N

2001-2002

N

n/a

Moderate

N

Y

All

1, 2, 3, 4, 8, 13, 15, 16, 18, 20

34.

Dominguez Channel Improvements

N

2001-2002

N

n/a

Low

Y

Y

J

2, 20

35.

Conduct study of truck yards, truck terminals, and ‘freight-forward’ users and its potential impacts in Carson

This activity was identified by the Carson Economic Development Committee as a potential Redevelopment Agency project.  Agency staff, however, considers this to be an issue best addressed by the Traffic and Circulation Element of the Carson General Plan, or in conjunction with other traffic/land use studies identified this Implementation Plan.

36.

Main Street rehabilitation and development from Del Amo Boulevard to 213th Street

N

2001-2002

N

1,000,000

High

Y

N

All

1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20

 

 

 

 

 

 

 

 

 

 

 

LEVEL THREE ACTIVITIES (Projects commencing 2003 or 2004)

37.

Redevelopment of Don Dominguez Apartments

N

2003-2004

N

n/a

Moderate

Y

N

A, B, F, G, H, K, L, M, O